Question: 1
An NEDC project is in the final planning stages. Several different teams will be working simultaneously, with critical junctions and timing issues. In order to manage workload with the IBM Virtualization Engine, a customer must have which of the following installed?
A. Virtualization Engine (VE) Console
B. EWLM with appropriate Domain Manager software
C. VIOS for POWER6
D. RDS
Question: 2
A growing customer is planning to upgrade their z990 to a z10. This requires cable planning to accommodate the connector differences. Which of the following resources should the NEDC Sales Leader recommend to perform this task?
A. IBM Systems Architect
B. IBM Customer Engineer
C. Customer Systems Programmer
D. Customer Hardware Planner
Question: 3
An international construction company is in the implementation phase of there NEDC project. The implementation team leader meets with you to discuss personality conflicts with one of the key customer departments. Which of the following actions are important for the NEDC sales leader?
A. Meet with the customer executive sponsor, describe the situation and inform the sponsor the department is placing the NEDC project at risk.
B. Meet privately with the customer department lead to understand the situation.
C. The issue now belongs to the implementation team, they must handle the problem.
D. Review the implementation plan, modify the plan to minimize the impact of the uncooperative department
Question:4
Infrastructure problems can inhibit a customer ability to innovate. Infrastructure problems can inhibit a customer? ability to innovate. What infrastructure problems can be addressed by consolidation and virtualization?
A. Server storage sprawl
B. Security breeches
C. Inefficient applications
D. High system utilization
Question: 5
A customer data is growing rapidly, increasing required backup time. Which of the following addresses the situation?
A. Higher capacity tape drives
B. Tivoli Storage Manager (TSM)
C. Assessment with data architect to identify root cause and solutions
D. NEDC Assessment Workshop
Answer:
1 .B
2.B
3.B
4.A
5.C
--By CertDumps Sales Team